Energy

Every member organisation of the Velocity Interoperability Network reports the energy used by its registered physical sites to the Environment Department of the Velocity Interoperability Network. Reports are made against the schedule set out under How to report and are used to publish aggregate energy figures for the Network, to measure progress against the efficiency targets and, through the factors published under Emissions and monitoring, to account for the emissions of every site on the same basis.

The requirements apply equally to every site whatever its size. A data hall drawing several megawatts and an office with a single equipment room report the same five figures, at the same intervals, in the same units. What differs is the effort involved, and the Department's guidance is written so that a small site can meet the requirements with a meter reading and a short message.

What must be reported

Electricity consumption
Metered electricity consumption for each site, reported quarterly in kilowatt-hours.
Fuel consumption
Fuel consumed by standby generators and heating plant, reported quarterly by fuel type.
Power usage effectiveness
Power usage effectiveness for each site that houses Network equipment, reported annually.
Low-carbon supply
The proportion of electricity supplied from renewable or contracted low-carbon sources, reported annually.
Supply capacity
Any change to a site's metered supply capacity, reported within 30 days of the change.

Refrigerant top-ups and cooling water drawn are reported quarterly alongside these figures, from the records kept by the site's maintainer. How they are used in the Network's emissions accounts is set out under Emissions and monitoring.

Efficiency targets

Power usage effectiveness of 1.4 or lower
At every site housing Network equipment, to be reached within three years of a site's registration.
A 3 per cent annual reduction
A year-on-year reduction of at least 3 per cent in electricity consumed per unit of installed equipment.
Half of electricity from low-carbon sources
At least half of each site's electricity supplied from renewable or contracted low-carbon sources.
No unnecessary generator running
No standby generator run for testing beyond the hours required by the site's resilience standard.

A worked example. The table below shows how the annual figures for a data hall are derived from its meters and its register entry.

Annual figures for a data hall with 250 kW of installed equipment
FigureValueSource
Total site electricity for the year1,400,000 kWhFrom the site's supply meter
Electricity consumed by Network equipment1,000,000 kWhFrom the sub-meter serving the equipment rooms
Power usage effectiveness1.401,400,000 divided by 1,000,000; meets the target
Electricity under a certified low-carbon contract770,000 kWhFrom the supplier's certificate
Low-carbon share55%770,000 divided by 1,400,000; meets the target
Installed equipment250 kW rated loadFrom the register entry
Electricity per unit of equipment4,000 kWh per kW1,000,000 divided by 250; compared with the previous year

Standby supply tests. The power standard requires the standby supply to be tested at full load. The frequency and duration of the test depend on the class of the site, and every test is reported to the Department within 14 days. Fuel burned in testing is counted in the quarterly fuel figure but is excluded from the calculation of electricity per unit of equipment.

Standby supply tests by class of site
Class of siteFrequencyDurationReported
Data hallQuarterly2 hours at full loadWithin 14 days
ExchangeQuarterly1 hour at full loadWithin 14 days
Transmission siteQuarterly1 hour at full loadWithin 14 days
Office with equipment roomHalf-yearly30 minutes at full loadWithin 14 days

A site that does not expect to meet a target may apply to the Department for a revised target, stating the reason and the date by which the original target will be met; the procedure is under How to report. Standards for the physical protection of sites are set out under Sites. Enquiries may be sent to contact@environment.gov.vin; common questions about metering, apportionment and low-carbon supply are answered in the frequently asked questions.

Reporting

Reports are made quarterly for consumption and annually for power usage effectiveness and the low-carbon share of supply. The calendar and the steps a member organisation follows are set out under How to report.

The first quarterly reports cover the fourth quarter of 2026 and are due on 30 January 2027.